Environmental stress screening (ESS) testing

Environmental stress screening (ESS) testing

The objective of the ESS test is to eliminate early death parts (including structural, material, manufacturing, shipping, and storage defects) as early as possible before they are assembled into the product to avoid the cost of midproduction impacting timetables and failure during the mission.

Stabilization Bake 1. Stabilization Bake

Based on MIL – STD – 883 Method 1008, Condition C rules, the electronic components into constant temperature box, the rated storage temperature, the temperature rise to parts for 24 hours of baking, this test does not need special design, mainly in the temperature and time, and pay attention to the heat source may not be directly radiation to the parts (through the fan power waft), all parts have any defect damage is not to test.

2. Temperature Cycling

Based on MIL – STD – 883 Method 1010, Condition B, for example, the electronic components into incubator, the temperature down to parts rated temperature storage place for 10 minutes, and then back to the room temperature at least 5 minutes, and then to part the rated storage temperature for at least ten minutes, so at least 10, its purpose in the test parts in high and low temperature changes, withstand the material properties, such as unbearable parts will be available by the seal test (including coarse leakage, leakage test) tested.

3. Constant Acceleration, Centrifuge

According to MIL-STD-883 and Method 2001 (the transistor and diode can be according to MIL-STD-750), the electronic components are placed in the centrifuge in the specified direction, and the electronic components are accelerated to the specified speed or predetermined G value. According to Condition E, the Y-axis is 30,00g.The purpose is to use the centrifugal force to show the bad structure of parts, such as bad wiring or bad sealing, which can be detected by electrical test and sealing test (including coarse leak test, fine leak test)

4. Seal Test

According to MIL-STD-883, Method 1014, seal test includes coarse leak test, fine leak test, poor seal is easily affected by environmental debris (moisture, dust, salt, acid, alkali, etc.).Therefore, the defective parts can be detected by sealing test. Both the coarse leak test and the fine leak test shall be performed according to the regulations. If there is no special regulation, the coarse leak test shall be performed first and then the fine leak test shall be performed.

5. Burn-in Test

According to MIL-STD-883,Method 1015(IC class) and MIL-STD-750,Method 1038(diode class)MIL-STD-750,Method1039(transistor class), the temperature and time of the parts to perform prefiring are specified, and MIL-M-38510 and MIL-S-19500 to specify the pre-firing circuit, applied bias, signal frequency range, and amplitude of the individual parts..

6. High and low temperature test

After the pre-burning test, the parts shall be tested for electrical function at the specified total operating temperature.

Electrical performance tests are divided into the following items:

An Incoming Accept Test for parts includes visual appearance and performance tests.

To order parts for environmental testing, identify model number, date of manufacture, name of manufacture, quality level.And the implementation of visual inspection of appearance, where there are damaged defects and not performance test.Normal temperature performance test shall be conducted for those who pass visual inspection.Environmental testing is performed after the performance test passes.

Pre-Burn-in Electric Test

After performing stable baking, temperature cycle, accelerated centrifugation, sealing test and other ring test items, perform normal temperature performance test before pre-burning, and mark qualified products appropriately. In this test, the defective parts in such ring test items as unstable baking, temperature cycle, accelerated centrifugation and sealing test are eliminated.

Pro-Burn-in Electric Test

Performance test shall be performed within 96 hours after cooling for 1 to 2 hours after pre-burning to eliminate defective parts.

 

1. The temperature of the neutral salt spray test chamber (NSS) is required to be at (35±2)℃, the humidity is greater than 95%, and the amount of fog reduction is 1~2mL/80cm*h. The nozzle pressure is 78.5~137.3kPa(0.8~1.4 KGF /cm2).In the salt spray test chamber, the salt water containing (5 ~ 0.5)% sodium chloride and pH value of 6.5~7.2 is sprayed through the spray device, so that the salt spray settlement to the test piece to be tested, after a certain time to observe the corrosion state of its surface.

 

2.copper accelerated acetate salt spray test (CASS) is to add 2 water copper chloride to 5% sodium chloride salt water on the basis of the general salt spray test, so that its concentration is 0.26g/L, and then acetic acid is used to adjust the pH, so that the pH value of salt spray collection solution is 3.1-3.3.(The test refers to GB/T 10125 man-made atmosphere corrosion test)

3. alternating salt spray test is a comprehensive salt spray test (alternating salt spray test chamber to achieve.

 

Acetate spray test (ASS test) is developed on the basis of neutral salt spray test.It’s a 5% sodium chloride solution with some glacial acetic acid.

Operation method of salt spray test chamber

1. Install the internal parts of the salt spray test chamber: tower spray device, funnel, round bar, V-shaped sample rack, etc.

2. Connect the air source, turn on the power switch after the power is connected.

3. Add water to the pressure barrel and the box. Stop adding water after the two low-water lamps are off. Add water to the sealing groove for sealing.

4, the pure water and sodium chloride salt with a ratio of 1:20.Pour the prepared solution into the test inlet (turn off the light with low brine).

5. After all the lights are off, we can turn on the operation, spray and timing switches, and turn on the defogging switch after the end of the test.

6. According to the test requirements, the equipment can be sprayed continuously and periodically (T1 and T2 tables are all set to 0 for continuous spraying; T1 is the working time and T2 is the rest time for intermittent spraying).

 

Precautions for salt spray test chamber

1, regular cleaning and maintenance of salt spray test chamber pressure barrel, salt water tank, nozzle.

2. Do not pour the sodium chloride solution out of the pressure barrel by manually adding water. Clean the solution measuring cylinder first and then add distilled water.

3. Do not clog the back exhaust pipe during the test, so as not to deform the box body due to excessive pressure in the box body.

4. Flammable and explosive articles should not be put into the box.

5. The pressure gauge behind the salt spray test box is 2kg and the front is 1kg. It has been designed by Dongguan Zhengtai Test Instrument Co., Ltd. before it leaves the factory, and please do not move.

6. If the spray quantity is insufficient, please raise the spray tower. If the spray quantity is too large, lower the spray tower (the standard for collecting the spray quantity is 1~2ml/h, and the average value of 16 hours)